Project Cost Management
-
one of the constraints in Project Management
-
usually measured in monetary value
-
goal is to complete the project within the approved budget
Significance
-
scheduling a project longer than it should be presents a higher risk of cost overrun
-
"weak area" of IT projects
Types
-
Rough Order of Magnitude
-
Budgetary Estimate
-
Definitive Estimate
| Estimate Type | When | Range |
|---|---|---|
ROM |
3 to 5 years before project completion |
-50% to +100% |
Budgetary |
1 to 2 years out |
-10% to +25% |
Definitive |
less than a year out |
-5% to +10% |
Please see: * Net Present Value * Return on Investment * Payback Analysis